We use cookies to ensure our site functions properly and to store limited information about your usage. You may give or withdraw consent at any time. To find out more, read our privacy policy and cookie policy.
Manage Cookies
A cookie is information stored on your computer by a website you visit. Cookies often store your settings for a website, such as your preferred language or location. This allows the site to present you with information customized to fit your needs. As per the GDPR law, companies need to get your explicit approval to collect your data. Some of these cookies are ‘strictly necessary’ to provide the basic functions of the website and can not be turned off, while others if present, have the option of being turned off. Learn more about our Privacy and Cookie policies. These can be managed also from our cookie policy page.
Strictly necessary cookies(always on):
Necessary for enabling core functionality. The website cannot function properly without these cookies. This cannot be turned off. e.g. Sign in, Language
Analytics cookies:
Analytical cookies help us to analyse user behaviour, mainly to see if the users are able to find and act on things that they are looking for. They allow us to recognise and count the number of visitors and to see how visitors move around our website when they are using it. Tools used: Google Analytics
Big decision 6: Future of the new Prebbleton Community Centre
Share Big decision 6: Future of the new Prebbleton Community Centre on FacebookShare Big decision 6: Future of the new Prebbleton Community Centre on X (formerly Twitter)Share Big decision 6: Future of the new Prebbleton Community Centre on LinkedinEmail Big decision 6: Future of the new Prebbleton Community Centre link
Consultation has concluded
A new Prebbleton Community Centre has been planned since it was proposed in the Long-Term Plan 2018–2028. Following consultation on the Annual Plan 2020/21 the project was deferred until this Long-Term Plan, so that more information on the location and community needs could be gathered. The demand for a new facility is clear, with the existing public hall being earthquake-prone and nearing the end of its life. This hall, which isn’t owned by the Council, has served as a focal point for community activities for many years.
Some further information is still required to understand the exact needs and the best site. To allow time to confirm this, we’re proposing to build the new community centre in 2025/26. Initial assessment work indicates that a flexible facility, which can cater for a variety of uses and age groups, is needed.
The most likely site for the proposed centre would be on Prebbleton Reserve, to strengthen this site as a community hub.
A new Prebbleton Community Centre has been planned since it was proposed in the Long-Term Plan 2018–2028. Following consultation on the Annual Plan 2020/21 the project was deferred until this Long-Term Plan, so that more information on the location and community needs could be gathered. The demand for a new facility is clear, with the existing public hall being earthquake-prone and nearing the end of its life. This hall, which isn’t owned by the Council, has served as a focal point for community activities for many years.
Some further information is still required to understand the exact needs and the best site. To allow time to confirm this, we’re proposing to build the new community centre in 2025/26. Initial assessment work indicates that a flexible facility, which can cater for a variety of uses and age groups, is needed.
The most likely site for the proposed centre would be on Prebbleton Reserve, to strengthen this site as a community hub.
Share Construct a new community centre on FacebookShare Construct a new community centre on X (formerly Twitter)Share Construct a new community centre on LinkedinEmail Construct a new community centre link
While exact needs and site are still being investigated, it’s expected that this proposed centre would be a multi-purpose facility, suitable for many different types of functions, and for a range of users and ages. It would also include some specialised spaces.
The facility would also have a high level of seismic performance, so it could be used as a civil defence emergency welfare centre for the district.
Cost
$6.3 million funded by a combination of development contributions paid by land developers, and borrowing. Plus ongoing operating and maintenance costs for the new facility.
While exact needs and site are still being investigated, it’s expected that this proposed centre would be a multi-purpose facility, suitable for many different types of functions, and for a range of users and ages. It would also include some specialised spaces.
The facility would also have a high level of seismic performance, so it could be used as a civil defence emergency welfare centre for the district.
Cost
$6.3 million funded by a combination of development contributions paid by land developers, and borrowing. Plus ongoing operating and maintenance costs for the new facility.
Impact on rates
The cost of the proposed new facility has a rate impact equal to $12 per year, which is already provided for within the budgeted Community Centres Targeted Rate and assumes the debt is repaid over 25 years.
Impact on debt
We would need to borrow an extra $4.9 million.
This would be repaid by the Community Centres Targeted Rate.
Share Defer the project to outside the 10-year plan on FacebookShare Defer the project to outside the 10-year plan on X (formerly Twitter)Share Defer the project to outside the 10-year plan on LinkedinEmail Defer the project to outside the 10-year plan link
Cost
There are no costs associated with this option.
Impact on rates
The Community Centres Targeted Rate will reduce by $12 per year compared with our forecast rate.
Impact on debt
No impact
Cost
There are no costs associated with this option.
Impact on rates
The Community Centres Targeted Rate will reduce by $12 per year compared with our forecast rate.
Impact on debt
No impact
Consultation has concluded
Quick poll
Consultation has concluded
Share What is your view on the future of the new Prebbleton Community Centre? on FacebookShare What is your view on the future of the new Prebbleton Community Centre? on X (formerly Twitter)Share What is your view on the future of the new Prebbleton Community Centre? on LinkedinEmail What is your view on the future of the new Prebbleton Community Centre? link